Corporate Business Alliance

CBA-COM · sample lesson

Chapter 1 · Free sample

The changeover, which is not a capacity problem

4 min read

Chapter 1 · The changeover, which is not a capacity problem01 / 09

Reframing the 55 minutes

The 55 minutes is not costing Rennick capacity. It is costing Rennick a schedule that cannot exist.

Slide 1 of 9. The 55 minutes is not costing Rennick capacity. It is costing Rennick a schedule that cannot exist.

The same lesson, in full

Rennick loses 12.83 hours a week of constraint time to changeover, which is 53% of all downtime and 8.5% of scheduled time. That much is arithmetic. The more important thing is what the 55 minutes does to the schedule.

Worked example 7: reducing the changeover across 14 changeovers a week

First, the mechanics. A changeover has internal elements, which can only be done while the line is stopped, and external elements, which could be done while it is still running but currently are not. The single largest gain in almost every changeover reduction is moving work from internal to external, and it usually costs very little.

Element Now (minutes) Classification After redesign
Run down and clear the line 6 Internal 6
Fetch tooling and consumables from stores 9 Internal, should be external 0
Change sealer die and tray guides 14 Internal 9
Change depositor nozzle and flush 11 Internal 7
Change label and film reels 5 Internal, prep externally 2
Find and load the recipe on the coder 4 Internal, should be external 1
First-off checks and sign-off 6 Internal 5
Total 55 30

Nine minutes of every changeover is somebody walking to stores. That is 126 minutes a week, 2.1 hours of the constraint, GBP 13,043 a week, spent fetching. The redesign costs a second set of dies at GBP 9,400, a changeover trolley at GBP 2,200, pre-staged reel trolleys at GBP 1,600, and standard work and training at GBP 3,500: GBP 16,700 in total.

Now the gain, computed honestly in two steps.

Quantity Arithmetic Value
Changeover time now 14 multiplied by 55 minutes 770 minutes, 12.83 hours
Changeover time after 14 multiplied by 30 minutes 420 minutes, 7.00 hours
Constraint hours recovered 5.83 hours
Units recoverable, gross 5.83 multiplied by 3,675 21,437
Gross value at GBP 1.69 GBP 36,229 a week
Units with unmet demand behind them from worked example 8 10,248
Net value against today's order book 10,248 multiplied by GBP 1.69 GBP 17,319 a week
Capacity left over 21,437 less 10,248 11,189 units, 3.04 running hours

Payback against the net figure is 16,700 divided by 17,319, which is under one week. Be suspicious of that, and say so before somebody else does: a payback of under a week is the signature of a benefit priced at a constraint against demand that is genuinely there. Both conditions have to hold. Check that the demand is real, that it is not conditional on a price the customer will not pay, and that nothing downstream of Line 3 becomes the new constraint once the extra 10,248 units start arriving. If despatch cannot handle it, you have moved the problem 40 metres.

Now the part that matters more than the capacity. Rennick runs 14 recipes and makes 14 changeovers a week, so each recipe runs once a week, in a batch sized to cover a week of call-off.

Constraint Value
Shelf life from production 8 days, 192 hours
Consumed before despatch (worked example 1) 53.1 hours, 2.2 days
Residual life the customer requires on receipt 5 days, 120 hours
Maximum age at delivery 3 days
Maximum time in finished goods after despatch readiness 0.8 days

Product made on Monday cannot lawfully serve a call-off on Friday. At best a single run covers three days of demand. That means every recipe needs to run at least twice a week: 28 changeovers, not 14. The weekly plan Rennick operates is not achievable, and the planner knows it, which is why the mix is wrong three days out of five and why the service level is 97.2%. This is not a scheduling failure by a planner. It is a design failure that the schedule is being asked to absorb.

Scenario Changeovers a week Minutes each Constraint hours consumed
Today 14 55 12.83
Twice-weekly runs at today's changeover 28 55 25.67
Twice-weekly runs at 30 minutes 28 30 14.00

Doubling the changeover frequency at today's 55 minutes would consume 21% of scheduled time and is unaffordable. Doubling it at 30 minutes costs 1.17 hours a week more than the site spends today, and makes the required schedule possible for the first time. That is the argument to take to the capital committee, and it is not a capacity argument at all. The exam will offer "reduce changeovers to gain capacity" as the plausible answer and "reduce changeover time so the mix can be run more often" as the defensible one. The second one is why the service level moves.

The full contents

Every chapter and lesson of the CBA-COM study material, with reading times and where the assessed workbooks fall.